BGRIM – 3Q26: Core profit inline; Long-term positive

BGRIM – 3Q26: Core profit inline; Long-term positive

BGRIM reported a 3Q26 core profit of Bt706mn (+71% YoY, +48% QoQ), in line with our estimate, driven by a sharp recovery in profit sharing from associates offset margin pressure from higher gas costs. While near-term 4Q26 earnings will remain pressured by elevated gas prices. Medium- to long-term growth is backed by 3,200–3,300MW in PDP2026 bidding opportunities, Direct PPA, data centers, and overseas renewable projects. We maintain OUTPERFORM with a mid-2027 TP is Bt26.5, based on a DCF valuation (WACC: 6.2%, LT growth: 1.5%).

3Q26 core up YoY and QoQ. BGRIM reported a 3Q26 net profit of Bt841mn (+61% YoY, +24% QoQ) on mark-to-market gains on Unison’s convertible debentures. Core profit came in at Bt706mn in 3Q26 (+71% YoY, +48% QoQ), in line with our expectation, driven by a sharp recovery in share of profit from associates to Bt445mn in 3Q26, reversing a loss of Bt169mn in 3Q25 and surging 354% QoQ, largely supported by the progressive COD of the Nakwol 1 offshore wind project (now 99% complete), alongside improved performance from KOPOS, Lohas, and IBS. However, SPP margins remained pressured by higher gas costs, which rose to Bt402/MMBtu (+Bt104 YoY, +Bt40 QoQ).

4Q26 outlook to impact from short-term high gas cost. We expect near-term performance to face pressure from higher gas costs, which are projected to average Bt400/MMBtu in 4Q26 before peak in 1Q27 and easing to a 2027 average of Bt350–370/MMBtu. To mitigate fuel cost volatility, BGRIM plans to import LNG 12 cargoes in 2027, covering roughly 30% of total gas consumption, alongside the government’s planned two-tier tariff restructuring to reflect actual costs for large users. Meanwhile, 4Q26 growth will be supported by new automotive and electronics IU connections toward its 20–30 MW full-year target.

Takeaway from meeting. The PDP2026 plan is expected to year-end 2026 approval and 1H27 bidding, where BGRIM targets developing 3,200–3,300MW across gas-fired plants (2,000MW), solar (up to 1,000MW), wind (200–300MW), and smart grid systems. In the data center segment, the 96MW Digital Edge joint venture (100% leased, 12–15% EIRR) has secured its US$880mn loan and BOI privileges in the EEC without impact from new cabinet rules, supporting full operation in 1Q27, expansion toward 500MW globally by 2030, and 30–40MW in new annual IU additions in 2027. Overseas projects are also advancing, led by South Korea's 364.8MW Nakwol 1 offshore wind farm, which is fully built and expected to contribute Bt300mn in full-year profit share in 2027, and Nakwol 2 (targeting late-2029 COD). To fund Bt34bn in committed capex and over Bt20bn in potential new investments toward its 10GW PPA target without an equity raise, management is pursuing asset monetization, such as bringing strategic partners into its SPP gas plants, to deleverage its net IBD/E ratio from roughly 2x.

Valuation/recommendation. We maintain our OUTPERFORM rating with a mid-2027 TP of Bt26.5, based on DCF valuation (WACC: 6.2%, terminal growth: 1.5%). This is backed by a positive medium- to long-term outlook and supported by several new opportunities, including PDP2026, Direct PPA, and the data centers.

Key risks. Higher gas cost and adjustment of Ft rate to catch up with fuel cost. Key ESG risks are the environmental impact from its exposure to fossil fuels, energy management, high greenhouse gas emission, and nearby community impact.